Bahrain's Flag Bahrain
Gen. Info. Industry Steel Links Steel News Ports Bahrain Links News

Steel News in Bahrain

 

Search Latest Bahraini Steel News

 
 

Bids due for Steel Framed Building for potline 5 at Alba
2003 January 16

 
Contractors are preparing bids by mid February 2003 for the main civils package on the 5th potline expansion at the Alu smelter of Aluminium Bahrain. It consists of the construction of a concrete steel-framed building, for lines 9 and 10 at Alba.
 

Bid for 3 storage tanks in Bahrain
2003 January 8

On 7 January 2003, bids were due for a contract to build three water tanks.
Each tank will store 10 million gallons of excess water produced by the coke calcinations plant of Aluminium Bahrain.
The project manager is UK’s Hyder Consulting The client is the Ministry of Electricity & Water.

The likely bidders were A.A. Nass Group, Ahmed Mansoor Al Ali, Panorama Contracting & Engineering , Nasser Abdul Mohammed Contracting and Airmech – all from Bahrain– and Hidada and Zamil Steel Industries, both from Saudi Arabia.
 

Asry steel work high in 3e quarter 2002
2003 January 1

Asry experienced a high demand for dry-docking and specialist services during the third quarter of 2002, continuing the trend set during the first half of the year. In all some five ULCCs/VLCCs were docked at the yard during the third quarter.
August saw little let up in the demand for
The level and diversification of vessels which used Asry during this period included Basrec's 6,000dwt floating dock and NPCC's LB-1 barge along with a number of bulk carriers and chemical tankers.
Steelwork repairs and renewals were high, totaling some 2,700 tons, which brings the year's total to date to 6,109 tons.
Owners from Bahrain, Iran, Kuwait, Saudi Arabia, Jordan and the UAE again provided Asry with the largest number of vessels during the first three quarters of 2002.
This was followed by strong support from Norway, Greece and the UK. Other countries sending vessels to Asry included Brazil, France, Egypt, Monaco, Cyprus, Romania and Russia.
 
 

Giant bridge piece hauled up into place.
2002 September 21

 

A HUGE structural steel bridge was erected for the Shaikh Khalifa bin Salman Al Khalifa Causeway yesterday.
The 404-metre, 2,000 tonne arch was lifted as a single unit and construction workers began welding it into place.
The work is expected to continue for two weeks.
Once completed the causeway will link Muharraq and Juffair.
The new bridge will be the major overwater connection of the 6.4-kilometre causeway.
It was built by Dubai-based Cleveland Bridge and Engineering in its Jebel Ali plant, then shipped piece by piece to Bahrain.
"The steel fabrication work of the bridge that we have done is about one third of the total BD14.5 million project cost," said managing director Michael Mack.
"It took more than eight months to build and fabricate the bridge."
Steel beams on the approach at both the Hidd and Juffair abutments were completed earlier this summer.
"The main arch span is 121 meters long and 40m wide, and rises to a height of 26m," he continued. "However, these will eventually function as three-lane carriageways," he noted. The main navigation span will have a high water spring tide level of 15.4m and a horizontal clearance of 115m.

"The main span is a bowstring arch structure with two pairs of arches, one on either side of the deck, each supporting a longitude tie member suspended by hangers," continued Mr. Al Kalali.
"Between these tie members spans transverse steel girders."
Mr. Al Kalali said a reinforced concrete top slab would form the deck. The causeway is expected open in November next year.
It is a joint venture between the Haji Hassan Group and Six Construct.
Project consultant is Hyder Consulting.
 

 

  To Submit your Steel Related News: click here